The City Rail Link is being officially opened today – as in, a ribbon-cutting, with trains commencing from Sunday. So with passenger services just two days away, what better time to take a look at look at how the rail network has been performing, to help provide a bit of a benchmark for the transformation the CRL delivers.
To start with, let’s look at the overall numbers before diving deeper.
Just over a century ago, Auckland’s rail network was carrying around 6 million annual trips. But the shifting of the Auckland Station from its original site where Waitematā now is, to The Strand, reduced the use of the network, putting it into decline.
The original iteration of something like the City Rail Link – the Morningside Deviation – was intended to address this by providing better access to the city centre but as we know, it never happened. What followed was, with a couple of exceptions, a slow and steady decline in the use of the network before reaching its nadir in 1993, with the system carrying a touch over one million trips.
That was when Auckland brought Perth’s former diesel trains, which resulted in usage more than doubling. While the diesel trains revived the network, it was the 2003 opening of Britomart Station – now Waitematā – that returned trains to where they originally were over 80 years earlier, which really kickstarted the rail revival in Auckland. It turns out, making the network a lot more useful results in usage shooting up.
Further improvements to the network, such as station upgrades, double-tracking of the Western line, the opening of the Onehunga and Manukau branches, and eventually electrification, saw usage rise even higher – peaking at just over 22 million trips prior to the arrival of COVID.
Since then, a rise in work-from-home has changed travel patterns, and the network has been impacted by six years of disruption (for various works), which has taken a massive toll on ridership. In the 12 months to the end of August 2026, there were just 14.7 million trips, which is about 67% of the pre-COVID peak. The last time usage was at 14.7 million trips was September 2015.
The growth of ridership post-Britomart was driven by numerous improvements to both the rail network and the wider public transport network. The version on the chart below looks just at the modern history a bit more closely, showing many of the improvements that contributed to the growth we’ve seen.
Notably, the years of disruption meant the rail network never recovered at the same rate as buses or ferries, and was stuck in the low-60% for years. It’s only in the last few months that we’ve started to see that change, pushing closer to 80% of pre-COVID levels. This is likely a combination of the reduction in disruptions, plus the impacts of fuel price rises.
Auckland Transport has also kindly provided me with station usage data. There are many possible stories to tell from this – too many for just one post.
To start with, here are the overall boardings. As you’d expect, even though usage overall is down, Waitematā continues to dominate, accounting for over a quarter of all boardings. At the other end of the scale, Te Mahia, at which AT have just built a large pedestrian bridge as part of their efforts to remove level crossings – is the least used station on the network with just 32k trips in the last financial year, not far behind Te Papapa.
And below is how station boardings compare to pre-COVID levels.
Only two stations are above what they were at in 2019: Puhinui and Parnell. The upgrade of Puhinui has clearly made a huge difference to its usage, a trend we’ve seen at other significantly upgraded stations in the past. Meanawhile, Parnell has benefited a lot from efforts to improve access, such as the underpass that was completed at the start of 2024.
The Onehunga line stations are the worst performing here. That will in large part be due to them no longer having direct access to Waitematā, like they had in the pre-COVID era.
Of the main lines, the Western looks to be performing the worst – likely a big part of this would be the ongoing network disruption due to the rail network rebuild works and the upgrade of Henderson station. As such, boardings at many of the stations are still down on even 2024 levels, with the outer stations down by as much as 20%.
However, that is just boardings, which actually accounts for around 52% of all trips on the network – something that will certainly start to change from next week.
If we extend the same logic to other stations, the top five are shown below. Note, a trip from one of these stations to another, e.g. from Panmure to Waitematā, will be counted in both, so the totals don’t add up to 100%. The results also highlight a few other interesting aspects:
- Panmure and New Lynn have continued to battle for the 3rd and 4th busiest stations. Panmure is now more clearly ahead, but as noted above, New Lynn has been disrupted more recently by network upgrades whereas Panmure saw that disruption more significantly in 2022-24.
- Manukau has continued to rise in popularity, with Middlemore only just behind.
Another interesting story using this method has been in the South. The closure of Pukekohe during electrification and the station upgrade clearly resulted in many users shifting to catching the train from Papakura and Takaanini. With Pukekohe reopened, those trips have shifted back. I imagine this picture will change a lot again with the opening of Drury and Paerātā, plus Ngākōroa next year.
The two stations with the biggest mismatch in boarding and alighting numbers remain Grafton and Waitematā. This suggests the ongoing presence of “down-hilling” – people are getting off the train at Grafton, perhaps catching a bus to areas like the University, then carrying on downhill in the afternoon, to board a homeward train at Waitematā.
If I rank each station by boardings and chart them all, I get what I like to call The Rug, due to its resemblance to a colourful woven rug thanks to all the movement.
For this version I’ve only highlighted the most dramatic changes. As you can see, most of the stations that have had big changes are those that have been through significant upgrades.
The data Auckland Transport provided me also included the rough time of day that trips occurred. Over half of all trips happen in the morning or afternoon peaks. Note: the off-peak figures include weekends and public holidays.
It will be fascinating to see how these numbers change over the coming weeks, months, and years.
For their part, Auckland Transport include their ridership targets – which are based off their modelled predictions – in their Statement of Intent (SOI) documents – the most recent one being signed off by Auckland Council just a few weeks ago and covering 2026-29.
The chart below shows the targets, including those from previous SOIs. It shows that Auckland Transport is expecting to reach 22 million trips again by the middle of 2028 and then only a slight increase to 23.3 million trips a year later.
In an interview with the Herald, KiwiRail CEO Peter Reidy mentioned that they’re preparing for 29 million passengers by the end of 2030. So I’ve added that too. As you can see, it represents a continuation of the trend predicted by Auckland Transport for the next few years, which does feel a bit more realistic.
Personally, these results feel a bit too low to me – but time will tell. It’s certainly something we’ll be watching closely.
What do you think will happen with ridership.










Processing...
On Eastern Line most passengers are pretty slow to get off the train once it arrives at Waitemata/Britomart as it’s a terminus. On Monday it will be a through station. I guess it will take a while for people to get used to, but I wonder what preparations have been made for this. Will there be extra (audible!) announcements? Hopefully additional staff to remind people to either hop off quickly, or stay on the train e.g. Auckland Girls students will probably find it easier to get off at K Rd. I wonder if they know that? Although we’re all interested in CRL I think most passengers will be surprised on Monday when the doors close early and then they’re all of a sudden in a tunnel going to Panic Stations 🙂
Also, I expect Waitemata/Britomart will go down quite a lot within the first week as people switch to Te Waihorotiu and K Rd. Will rebound in the medium term as the whole network gets more popular, wonder how long that will take to get back to today’s levels? Not a bad thing as Waitemata can get quite full at peak.
Agree on the drop, but I don’t foresee Waitemata station getting dethroned from the top spot. So much more livelier in that part of the city. The Britomart regeneration and activation of the space is just amazing to see
Yeah, although it might take 6 months plus to settle down. A lot of existing and new riders will go to the new shiny stations for a while before they figure out what works best for them.
One possibility is that K Rd becomes the designated Uni station because of the downhill effect. TWH is closer but needs an uphill climb up Albert. Also because of general vibe of K Rd. And for East and South they might go to K Rd in morning, walk down to Uni, then walk down to Waitemata for home trip.
Re below, I mean an uphill climb up Victoria St East and then Albert Park
It’ll be intersting to see how the CRL changes travel patterns to/from the Universities. Have noticed a lot of students catch 70/27 from Waitemata up to the Univesties (and a bus down to Waitemata when leaving).
As someone commented in the previous rail ridership post, we need a colourful rail station rankings graph on a shirt or a blanket!!
Grafton is going to drop like stone.
You forgot to add buses partonage.
Grafton is going to drop like a bomb.
You forgot to add bus partonge.
Fare avoidance is a very big issue on the western from my personal observation. I bet (atleast) another fourth of ridership would come in if all of the people avoiding fares started magically paying them.
It’ll improve because instead of Grafton people will be choosing between K Rd, Mt Eden or Aotea, all of which are gated rather than Grafton Rd which is yet to be.
Realistically they should be prioritising gating Grafton/Parnell as people can (and will) still travel slightly longer to avoid paying fares.
Parnell been gated for probably a couple of years.
Looking forward to a new era in mass transport for Auckland.
Pukekohe station upgrades stand out in your “rug” with near 2 years being closed.
The trains were still running, freight at least, just no people trains. We’re past it now and locals are shifting back from their cars.
Really hoping the “close it for years to upgrade” logic belongs to the smaller slower city planning era we’ve now left behind.
Now, to link up these new stations with walking and cycling paths – more than just road connections.
A century ago, every person must have caught the train. Post World War Two, every person drives a car.
The Central Rail Link is a project from more than a century ago, so it proves the longevity of train travel; particularly in regard to mass transit.
One hundred years ago our population was how many? In the tens of thousands? And still six million train rides. Now we have a million or so, and only a minority appear dedicated to trains.
The Central Rail Link is a fix for a problem imagined more than a century ago. It is our city’s chance to prove that we care about the people that live here; not about the awful private motor vehicles that are almost as big as the bus in some instances.
For our tamariki, mokupuna, supergold card holders especially, the Central Rail Link will make car travel seem silly, stressful, and a waste of time, space and life.
Trains are the lifeblood of every city in the world, they will be ours.
Also, if anyone knows how to make David Seymour stop saying horrible things for a few seconds, I do not believe that fascism should have any place in our motu, and what we have in NZFirst and ACT is very similar to AFD in Germany. Fascism was invented by the Italians, perfected by the Germans, but we do not need it hier!!!
bah humbug
To whoever made the Rail Boardings graphs…
Bravo on the colour scheme, I don’t think I have ever seen something that so clearly shows where lines merge and split without additional notes before. That is a thing of beauty.
It seems like the Kiwi Rail CEO let slip an internal target with AT insisting on a public target that will be easily met. Not sure i like this strategy. But if there is a more ambitious internal target that is at least better than if there’s only the soft official one.
Targets do get aimed at. So i would rather there is, somewhere, an ambitious stretch target for AT teams to focus on, have to get creative to meet, etc.
30m by 2030 looks good to me. 30 by 30!
A doubling.
A presentation of actual passenger journeys pre and post CRL opening would be very interesting. Particularly so for the trips where direct access has gone ie Western Line to Grafton, Newmarket and Parnell.
I suspect politicians are going to want to jump on the rail bandwagon assuming the CRL is a big success.
So if National get elected, and they want to build rail, and they don’t want to build LR because they are National, what projects could we expect? Will we see the Avondale Southdown designation used for metro rail? Or could they revive metro rail to the airport via Onehunga?
As if any politician knows how a mix of rail modes might be right for any given city in NZ.
I think that the downtown to airport via Puhinui is ok. I know lots of overseas cities have direct to airport rail/light rail setups, but the cost of extending from Onehunga to the airport might outweigh the good that same money could do elsewhere on the system.
There are big projects coming up, level crossing removal, harbour crossing and maybe the Southdown link.
All of those should rank ahead of an airport rail link IMHO.
Melbourne has, and is, making absolutely massive investments to upgrades and extensions to its already huge suburban rail network.
But connecting this huge network, to it’s airport, one much bigger then Auckland’s, still remains relitively low on it’s priorities.
In Brisbane there is a direct train from the city to the airport. It costs $AU23.50 one way. It is the same 1067 rail gauge as the QR system, but has rolling stock suitable for travellers with luggage etc.
But here’s the catch, it is contracted out to a private operator with something in the region of 10 to 15 years to run. I am guessing that politicians had their sticky fingers all over that deal. I contacted a relative who has used it regularly and he reports it is very lightly used, and never crowded. If it was run by QR it would be a 50c fare introduced recently on suburban bus and train systems, but even before that the fare would have been about $AU5.00.
Let’s hope any such arrangements in NZ (Christchurch maybe) are not so expensive that ridership is low.
I work part of the week around Grafton. People I work with can’t come to terms with the fact you can either when coming from the west, time it right and change to O-W at Maungawhau for Grafton, or… just change at K-rd.
Oh no… you have to change trains…like…in a real city! They could also just take the INN link from K-rd or walk. Much whinging from the general populace who don’t really seem to understand how transit works. Or large infrastructure projects in general either. I imagine many of you fellow GA readers have similar discussions at work.
Enjoy all your info that you supply in your articles. How do you get people out of cars, we don’t have a huge population that gives enough support for the various modes of transports the likes of Europe.
Auckland is a big city for its level of transit in European terms. There a population of 200k means transit and trams etc.
We do not lack for people, we have lacked a supply of good enough services for people to use, that is being addressed. There are other factors such as urban form and pricing that also matter too. Change is happening.
In terms of pedestrian bridges to reduce level crossings, why did they start with the modest Te Mahia station and patronage?
They’re focusing on lines. So priority #1 is Southern Line as that’s where KRs freight is. Now they’re reaching the point that essentially every crossing has been closed on the lines freight uses, they’re getting to the Western Line, first the bit to the Avondale – Southdown junction, then next to Henderson, then to the edge of the network. Last will be Onehunga (as we don’t really know the plans for it post Avondale – Southdown)
Looking forward to reading about the post CRL stats.
Decided to take a look at what the Greater Auckland post from 10 years ago out of curiosity and its bang on about the CRL being imminent. Kinda ironic that it’ll open on the same day (a decade ago) that it was posted.
https://www.greaterauckland.org.nz/2016/09/13/city-rail-link-and-atap-imminent/
Very very excited about the CRL opening on Sunday. Hoping it’ll be the catalyst to more public transport projects similar to Waitemata station over 20 years ago.