For some reason when Auckland Transport released information on February public transport patronage late last month I never quite got around to looking at much more than the headline statistic – that public transport patronage is now at a 60 year high. If you do take a more in depth look at the statistics there are some interesting trends to focus on.
To start with though, here are those headline stats:
Boarding as a whole up by 8.3% compared to February last year, rail up by almost 18%, the Northern Express bus up by over 20%. Those are some pretty impressive numbers – reflecting the fact that petrol broke through $2 a litre in February, as well as the fruition of service improvements (particularly to rail) throughout 2010.
If you break down the patronage, it’s great to see our regular buses doing quite well – with a 7.3% increase in patronage on buses other than the Northern Express. Over recent years patronage growth on the bus system has been sluggish – due to the fact that ARTA tended to ignore it in favour of more high-profile rail improvements. It’s good to see buses pick up though, as they really are the bulk of Auckland’s PT network:
One very notable piece of information is highlighted in red above – patronage on the Onehunga Line. Before it opened, ARTA had expected the line to attract around 500 trips a day. With nearly 55,000 trips throughout February that’s close to 2,000 a day – four times what was expected! I am incredibly pleased that this line has been so successful – it must be very rewarding for those who fought so long and so hard to see it reopened.
The graph below shows the longer term trends. I’m very much looking forward to seeing March’s data – to see 1 million rail trips a month being achieved for the first time:
While the gap between the orange and black lines has clearly widened in recent years, it is still clear that fluctuations in bus patronage have the biggest impact on total patronage levels – as after all the vast majority of Auckland’s PT trips are by bus. Nevertheless, patronage growth remains fastest on the RTN (rail + Northern Express) part of the system:
If we look a bit closer at the bus patronage data, we can clearly see the huge impact that the October 2009 bus lockout had, with October 2010 showing a massive rebound in boardings from the year before. This has boosted overall growth – particularly in the isthmus part of the network that has been sluggish in recent years:
The highest growth areas continue to be in the north and south. What’s good about this trend is that these are likely to be quite long trips, and getting people to take long trips by public transport has a bigger impact on reducing traffic than eliminating short trips. Hopefully the changes to inner Auckland bus routes proposed in the last few weeks might boost patronage in the isthmus sector once they’re implemented.
Finally, as the graph below shows, ferry patronage increased by a significant 12% in February:
This is a welcome increase, and along with other significant months in October and November it seems that ferry patronage might finally be getting out of the rut it’s been in for the past few years and is starting to grow. As the new Hobsonville wharf comes online, to serve the development happening around there, we should see further increases.
All up, February was a month of really solid PT patronage growth right across the network, on all types of modes and it would seem in all parts of the region. I look forward to March stats as they should be spectacular.
Processing...
I was just looking at some of this yesterday and saw some interesting results.
1. In 2002 annual rail patronage was only 4.6% of all PT trips however now it makes up 14.4% of all trips while ferries have remained relatively stable.
2. The average number of rail trips per day (including weekends) during Feb was the highest we have seen so ever at 29,928 per day, just eclipsing March last year although it should be noted that this doesn’t take into account that Easter fell in March last year. We already know that March passed 1 million trips so that puts the daily average up over 32k
In 1992 there were just over 1 million rail trips. March 2011 alone will have more rail trips than all of 1992.
The nearly 2000 people per day using the Onehunga service is a figure arrived at only by adding Southern Line passengers. After the trains depart Onehunga, Te Papapa, Penrose and Ellerslie, the staff then count the passengers. Southern Line passengers using Ellerslie and Penrose are therefore included in the count. The actual number of people using the Onehunga line is a few hundred per day. Essentially the branch’s success is being claimed only after fudging the figures. However, even at a few hundred per day, it’s doing well. I do wish they would be more honest with the figures though.
Great to hear that the Onehunga line is doing so well (even if the figures are somewhat dubious). As a frequent passenger I would like to see offpeak services having a frequency of at least 2tph. Currently, if you happen to miss the 9.45am train to Britomart, you have to wait 1hr15 until the next one-which is ridiculous for most passengers who have a commitment such as a meeting or class.